Development Works at Spelthorne Leisure Centre

Exciting improvements are coming to Spelthorne Leisure Centre!

To ensure you are kept up to date with all the changes happening at the centre, please keep reading to learn all about the potential parking disruptions at the current facility and how the new Spelthorne Leisure Centre will look once it is built on the adjacent site.

Spelthorne Developments

Developmental Works Timeline

Week 1: 18/07/22 – 22/07/22

  • Temporary carparks being constructed for future public use
  • Relocate cycle racks as a temporary measure

Spelthorne Development

Week 2: 25/07/22 – 29/07/22

  • Temporary carparks being constructed for future public use

Spelthorne Development

Week 3: 08/08/22 – 12/08/22

  • Temporary carparks being constructed for future public use

Spelthorne Development

Week 4: 15/08/22 – 19/08/22

  • Temporary carparks planned to be opened for public use with disabled spaces

Spelthorne Development

Week 5: 22/08/22 – 26/08/22

  • Temporary carparks planned to be opened for public use allowing drainage works to commence in rear carpark in the area shown only. Disabled parking spaces will be available in both temporary car parks. The rear carpark will remain open with reduced spaces.