Great News – Brand New Westway Fitness Club Gym Coming Soon

Everyone Active and Westway Trust are investing £1m at Westway Sports & Fitness Club in its ambition to provide world class facilities to support both organisations’ joint aim of getting 1.2m people more active.

Please see information below regarding timelines and frequently asked questions relating to the refurbishment, as well as the women only session schedule.

Timeline*

When does the work start and finish?

The works are scheduled to start on Monday 12th February and will last for approximately 16 weeks. A timeline of proposed works is shown below:

Changing Rooms Closures

Area Closes Reopens Temporary location during works
Womens changing room Monday 9th April Saturday 26th May Community changing room

Studio Closure

Area Closes Reopens Temporary location during works
Studio 1 Monday 19th March Saturday 5th May Westway Sports & Fitness Centre (1, Crowthorne Rd, London W10 6RP)
Studio 2 (Indoor cycling studio) Thursday 1st February Friday 1st June Westway Sports & Fitness Centre (1, Crowthorne Rd, London W10 6RP)

Gym Closures

Date Closing time
Monday 23rd April and Tuesday 24th April All day

Gym Works Schedule

Area Close Reopen What’s happening
Phase 1
Stretch and resistance
Sunday 25th Feb from 4pm Monday 26th March from 6.30am Section will be closed for refurbishment.  The Cardio area and Weights room
will remain open with a revised gym layout and reduced kit.
Phase 2
Cardio area
Sunday 25th March from 4pm Wednesday 25th April from 6.30am Section will be closed for refurbishment.   The Stretch and resistance area and Weights room will remain open with a revised gym layout and reduced kit.
Phase 3
New kit installation
Monday 23rd April Wednesday 25th April from 6.30am New kit will be installed in the Stretch and resistance and Cardio areas.  Weights room closes for final phase of refurb.
Phase 4
Weights room
Sunday 22nd April Monday 21st May from 12 noon Section will be closed for refurbishment.  The new Stretch and resistance and Cardio areas will be open.
Whole gym reopens on Monday 21st May from 12 noon

The project completion date is 1st June 2018.

Sunday Women Only Schedule April- June 2018

April 2018

Sunday Women only sessions will continue as usual in April with the following exceptions:

Sunday 1ST April – NO Women Only Session (Easter Weekend)

Sunday 22nd April – NO Women Only Session

Sunday 29th April – NO Women Only Session (Bank Holiday Weekend)

May 2018

There will be NO Sunday Women Only sessions in May 2018.

June 2018

Sessions will resume on Sunday 17th June 2018 after Ramadan.

Access and changes

Will any parts of the Fitness Club be out of use during the works?

Yes, the areas above will be closed whilst works take place. We are going to be a little upside down until the works are completed, however our build contractors have worked alongside us for years and understand the need to minimise disruption, noise and mess. Alternative facilities and activities will be provided wherever possible.

Gym floor – we don’t anticipate having to close the whole gym floor for any extended period, however, the works will be completed in 4 phases, requiring areas of the gym floor to be closed for each phase.  We will reduce the amount of cardio and resistance kit available in the remaining space. There will be some full day gym floor closures during the phases to allow for the relocation of kit from one area to the next.

Studios – The group cycling studio will be closed throughout the duration of the works (1st February – 1st June), with group cycling classes available at Westway Sports & Fitness Centre during this time.

Studio 1 will be closed for refurbishment for 7 weeks (19th March – 4th May), during which time most of the classes will be moved down to Westway Sports & Fitness Centre.

Changing Rooms – please see schedule above and our information boards in the Club which will provide more information about the changing room refurbishment.

We will relocate members to the Community Changing Room during works in the men’s or women’s changing room, a sauna is available in here.

Disability Access during works

The Accessible Changing room will not be available throughout the works.  Access to other parts of the Club will be limited for those with mobility issues and there will be limited Inclusive Fitness Initiative (IFI) equipment available during the refurbishment works. Our regular IFI support sessions and group sessions will be relocated to Westway Sports & Fitness Centre for the duration. If you have any special access needs please speak to a member of the team who will be able to help you to access Westway Sports & Fitness Centre.

Can I use other centres during the works?

Yes, we would encourage all Fitness Club customers to use the brand new gym, studios and changing facilities at Westway Sports & Fitness Centre during the works. This will give you a really good idea of the type of equipment and look and feel of what the new Fitness Club will look like.

What’s new?

  • New gym (resistance, weightlifting, cardio and functional training areas)
  • New studios
  • New equipment (Technogym, Keiser indoor cycles, Wattbikes and new group exercise kit)
  • New changing rooms (including flooring, showers, toilets, lockers, vanity areas, sauna and steam)
  • Refurbished squash courts
  • New air conditioning / ventilation
  • New group exercise timetable
  • New squash programme

How do I found out more information about the developments?

To find out more about the developments and updates on progress, watch this space, follow us on social media (Facebook: @WestwayFitness, Twitter: @Westway_Fitness) and via updates via the Everyone Active app.

We will regularly update you via social media and in-Club information so would encourage you to check that we have your correct email address.

Colleagues will be onsite at all times to help and answer questions throughout the works.

*Please note that although these are the planned dates, they may be subject to change due to unforeseen circumstances and we will keep you informed of any changes as soon as possible