Welcome to the August edition of Holly Hill Leisure Centre Newsletter.  As you can see, things are moving along at a good rate and we are still on course to finish next summer.

Work to construct the main swimming pool tank is underway.

construction1

Construction of the basement that will hold the plant and equipment to serve the main and learner pool is progressing well.

construction2

Blockwork walls are being constructed above the concrete foundations; these will support the pre-cast concrete ground-floor slab with drainage and service ducts running beneath.

construction3

The construction of the new junction from Barnes Lane is on target for completion by the end of August and the temporary traffic lights will be removed before the new school term starts.

construction4

Schedule

The project remains on schedule and the construction works should be completed early in July 2016. At this time the building will be handed over to Everyone Active who will manage and operate the Leisure Centre on behalf of Fareham Borough Council.

Should you experience any problems with the works, please contact the Balfour Beatty in the first instance:

Jon Chew (Site Manager): jchew@balfourbeatty.co.uk

If you wish to contact Fareham Borough Council about the project then please contact:

Gareth Satherley: gsatherley@fareham.gov.uk