Your New Taro Leisure Centre

Key Dates ↓ | Enquire Online

Everyone Active and East Hampshire District Council have invested £2.8million to significantly improve the facilities on offer at Taro Leisure Centre. The final works are now underway, with all areas of the upgraded centre due to reopen in December.

The fitness suite is currently undergoing a transformation that will offer members access to a greater range of fitness equipment. It is being extended to include 100 state-of-the-art fitness stations as well as a new free-weights and functional training area, which will be available to enjoy at the end of November.

Equipment

Read More

State of the art of equipment will also be added to the centre including:
• 2 new skill mill trea

Read More

On top of this, the final phase of the project will also unveil a modernised reception, refurbished fitness changing rooms and a new soft play area.

“I am really excited for the completed project to be unveiled. It has already made a big difference to customers who use the new studios and pool-side changing area, and this final stage will see even more people benefiting from the upgrades. Taro Leisure Centre is a hub of activity for the local community, and investments like this ensure it continues to meet the needs of customers. I want to thank all our members for their patience while the works have been ongoing, and look forward to welcoming them into the fully renovated centre soon.”

Mark McDowell, Everyone Active’s general manager

The development has been completed in stages, and has already seen new group cycling and health and wellbeing studios installed, as well a significant refurbishment of the pool-side changing area.

The community will be invited to celebrate the completion of the project at an event held in the New Year. Taro Leisure Centre will be opening its door for free and encouraging visitors to try out the new facilities alongside some well-known sporting faces.

Key Dates

Key Dates to look out for:

Friday 26th October – Wednesday 28th November – Final construction work will be taking place to extend and improve the fitness suite. During this time you may notice contractors working in the area and some increased noise, however we will keep all disruption to a minimum.

Tuesday 30th October – The fitness suite will close slightly earlier than normal at 8pm. This is to allow for equipment to be temporarily set up in the newly-extended area of the gym, while the existing gym space is briefly closed for renovation.

Wednesday 31st October – The temporary gym set up will reopen at the normal time in the newly-extended area. Throughout the relocation we have made sure you will still have access to all the gym equipment that is currently available.

Wednesday 21st November – You will begin to see new state-of-the-art Technogym fitness equipment being installed.

Thursday 29th November – All areas of the gym will fully reopen and all existing kit will be replaced with brand new equipment. You will have access to a new free-weights area and more than 100 upgraded fitness stations.